When and why this scorecard runs
This scorecard is the mid-program readiness instrument inside a HITRUST r2 engagement. It is run at the boundary between month 4 and month 5 of the eleven-month program described in the paired guide, HITRUST r2 Certification: An 11-Month Realistic Roadmap, the point at which readiness has closed (months 1 to 3), remediation has been live for four to six weeks, and the validated assessor engagement (months 8 to 11) is close enough that the calendar cost of bad news has become real. Run it earlier than month 4 and there is nothing to score; run it later than month 5 and the remediation runway is too short to matter.
It is run jointly by the org's compliance lead (the named MyCSF owner described in the roadmap) and the outside readiness partner, which is the Securem partner where we are engaged. The compliance lead provides the evidence; the partner grades. Where the two disagree on a score, the lower of the two is taken. The discipline of the rubric is in its conservatism, because the assessor will be more conservative than either of you.
What this scorecard forecasts is the likelihood of a first-attempt validated certification at the maturity levels the org has chosen to target. HITRUST's maturity model has five levels (Policy, Procedure, Implemented, Measured, Managed). HITRUST describes r2 as evaluating policy, procedure, and implementation, with Measured and Managed above those, so confirm with the assessor which levels the assessment will score. HITRUST sets its own scoring rubric and certification thresholds, and this scorecard does not restate them. What it does not predict, and does not replace, is the QA exchange between the validated assessor and HITRUST itself. HITRUST's QA is its own variable, and it is one no readiness instrument can fully model. A high score here means the assessor will have a clean submission to send up; it does not bind HITRUST's response.
Scoring rubric
Every item below is scored on a 0/1/2 scale.
- 0: Not in place or not defensible. The control or artifact is missing, the implementation is incomplete, or the evidence cannot be produced in MyCSF on demand. Default score on first pass for any item the compliance lead cannot show the assessor.
- 1: Partial / in flight. The control exists in some form: typically Policy and Procedure are in place and Implemented is partial; where Measured and Managed are scored, they are absent. SOC 2 Type II posture frequently grades at 1 across the technical domains on first pass.
- 2: Defensible at the targeted maturity levels. Every maturity level the org is targeting for the control is evidenced in MyCSF, with the operative practice tying back to the scoring narrative.
Each item scores 0, 1 or 2, and each section carries the weight in its heading. Convert a section's raw points to its weight: section score = raw points ÷ raw maximum × section points. Section C, for example, has seven items, a raw maximum of 14 against a weight of 15, so a raw 10 becomes 10 ÷ 14 × 15 = 10.7. Add the eight section scores and round to the nearest whole number. The total possible score is 100 points, distributed across eight sections weighted toward the control families where mid-market r2 first attempts tend to fail. The pass threshold is 80. That is this scorecard's own readiness bar for a first-attempt validated certification, not a HITRUST score.
Section A: Scope and MyCSF (10 points; 5 items, raw maximum 10)
| Item | 0 | 1 | 2 | Notes |
|---|---|---|---|---|
| Scope is a defensible single boundary, not patchwork | Scope is multiple disjoint systems with no unifying narrative | Single boundary drafted, edge cases (shared services, dev/test) unresolved | Single boundary, factor selection documented, edge systems explicitly in or out | Assessor will defend this to HITRUST QA |
| MyCSF subscription active and assessor granted access | Subscription not yet purchased or expired | Subscription active, assessor access not yet provisioned | Subscription active through certification window, assessor read access live, internal edit roles defined | Subscription duration must cover full certification cycle |
| Control inventory tied to scope and authoritative sources | Control list is generic, not scoped | Scoping engine output accepted, factor rationale not documented | Tailored control set generated from documented factor selection, mapped to NIST 800-53 / HIPAA / ISO inheritance | Drives every downstream evidence task |
| Targeted maturity levels declared per domain | No maturity targets set | Maturity targets set globally, not per domain | Per-domain maturity target set, agreed with readiness partner, recorded in MyCSF | Set the targets against HITRUST's current scoring rubric |
| Evidence library structure live in MyCSF | Evidence in shared drives, not in MyCSF | Evidence library exists, structure is ad-hoc | Library structured by control family, naming convention enforced, assessor can navigate without help | Saves time in months 8 to 9 |
Section B: Identity and access (15 points; 8 items, raw maximum 16)
| Item | 0 | 1 | 2 | Notes |
|---|---|---|---|---|
| Single IdP across in-scope workforce (AC-2 family) | Multiple directories, no consolidation plan | Consolidation underway, dual directories still authoritative | One IdP, all in-scope workforce migrated, legacy directories disabled and evidenced | Foundation for every AC and IA control |
| Phishing-resistant MFA on privileged roles (IA-2) | Admin MFA optional or SMS-only | TOTP MFA enforced, FIDO2 not yet rolled | FIDO2 / passkey MFA enforced on all privileged roles, break-glass governance documented | Targeting Measured means showing a metric for enforcement |
| Access provisioning tied to documented role design | Ad-hoc provisioning, no role catalog | Role catalog exists, provisioning still partly manual | Role-based provisioning automated through IdP, exceptions ticketed | AC-2, AC-5, AC-6 evidence chain |
| Quarterly access reviews running with evidence (AC-2(j)) | No periodic review | Reviews run, evidence in email or spreadsheets | Reviews on documented cadence, approver named, exceptions tracked, evidence in MyCSF | Measured maturity requires the metric, not just the review |
| Privileged session monitoring and logging (AC-17, AU-2) | Privileged sessions not logged | Sessions logged, not reviewed | Sessions logged, alerted on anomaly, monthly review evidenced | Common assessor probe |
| Offboarding closes within documented SLA (AC-2(h)) | Offboarding untracked or > 7 days | SLA exists, breached on a measurable share of cases | SLA met and measured monthly, exceptions tracked to closure | Tie to HR system of record |
| Service-account inventory with named owners and rotation cadence (IA-5) | No inventory | Inventory exists, owners not all assigned | Every service account has human owner, purpose, last rotation, scheduled rotation | Lateral-movement path; assessors target this |
| Third-party / external party access governed (AC-20) | No review run | List exists, decisions not executed | External party access reviewed quarterly, decisions executed, evidenced in MyCSF | Includes BAA-covered third parties |
Section C: Risk management and vendor program (15 points; 7 items, raw maximum 14)
| Item | 0 | 1 | 2 | Notes |
|---|---|---|---|---|
| Enterprise risk register on documented cadence | No register or stale > 12 months | Register exists, cadence not documented | Quarterly refresh, named risk owners, treatment decisions recorded, leadership review evidenced | Measured maturity requires the cadence metric |
| Risk assessment methodology documented and applied (RA-3) | No methodology | Methodology in policy, not applied to assessments | Methodology documented, applied to in-scope systems, evidence trail to register | Includes likelihood / impact scoring scheme |
| Third-party inventory complete with risk tiering (SR-3) | Vendor list in spreadsheet, no tiering | Inventory exists, tiering ad-hoc | Inventory tied to AP and SaaS admin consoles, tiering methodology documented, every vendor tiered | Reconciled against AP and IdP |
| BAAs in place for every vendor handling PHI | Gaps known and unresolved | Gaps closing, residuals tracked | All BAAs current, executed copies in evidence repository, renewal cadence | Healthcare-specific blocker |
| Tier-appropriate vendor assurance evidence collected | Assurance evidence not collected | SOC 2 collected for some vendors | Tier-driven assurance (SOC 2, HITRUST, pen test, questionnaire) collected, reviewed, dated | The bar is review, not collection |
| Vendor reassessment cadence documented and running | No reassessment | Reassessment run informally | Reassessment cadence per tier, evidenced in MyCSF, on schedule | The Measured maturity question |
| Vendor offboarding process documented and evidenced | No process | Process in policy, not evidenced | Documented process, evidence on at least one offboarded vendor in the last 12 months | Often-missed control |
Section D: Endpoint and cloud baseline (15 points; 7 items, raw maximum 14)
| Item | 0 | 1 | 2 | Notes |
|---|---|---|---|---|
| EDR deployed on 100% of in-scope endpoints (SI-3) | EDR partial or off some endpoints | EDR deployed, coverage gap < 5% | 100% coverage, gap measured weekly, exceptions ticketed | The coverage metric is the artifact |
| Endpoint hardening baseline documented and enforced (CM-6) | No baseline | Baseline documented, drift not measured | Baseline enforced, drift measured, remediation SLA met | CIS or vendor-published baseline acceptable |
| Patch SLA documented and met by severity (SI-2) | No SLA | SLA exists, breached on critical | SLA met for critical / high, measured monthly, exceptions evidenced | Critical = 7 days is typical |
| Vulnerability scanning on documented cadence (RA-5) | No scanning | Scanning in flight, results not triaged | Authenticated scans on cadence, results triaged, remediation tracked to closure | Authenticated, not unauthenticated |
| Cloud security posture management (CSPM) live (CM-2 / cloud) | No CSPM | CSPM deployed, findings unreviewed | CSPM live, findings triaged on cadence, exceptions tracked | AWS Config, GuardDuty, Defender, Wiz, Prisma, vendor-agnostic |
| Configuration management baseline for cloud workloads (CM-2) | No IaC or drift detection | IaC in place, drift not detected | IaC enforced, drift detected and remediated, evidence in MyCSF | Terraform / CloudFormation acceptable |
| Encryption at rest and in transit evidenced (SC-13, SC-28) | Encryption claims not evidenced | Evidence partial | TLS / KMS evidence per system, key management documented, rotation cadence | Includes BYOK where contractual |
Section E: Audit logging and detection (15 points; 7 items, raw maximum 14)
| Item | 0 | 1 | 2 | Notes |
|---|---|---|---|---|
| Log sources inventoried against in-scope systems (AU-2) | No inventory | Inventory exists, gaps unmeasured | Inventory complete, mapped to in-scope systems, gaps closed | Foundation control |
| Logs forwarded to central destination (AU-6) | Logs local to systems | Some sources forwarded, partial | All in-scope sources forwarded to SIEM / log lake, retention met | Splunk, Sentinel, Datadog, Chronicle, vendor-agnostic |
| Log retention meets policy and authoritative source (AU-11) | Retention not configured | Retention partial | Retention configured per source, evidenced, periodic test of retrieval | One-year retention is typical floor |
| SIEM correlation rules tuned to environment (SI-4) | Default rules only | Custom rules in flight | Rules tuned, false-positive rate measured, monthly tuning evidenced | Measured maturity question |
| Alert routing to named on-call (IR-4) | Alerts to shared inbox | On-call rotation exists, not documented | On-call documented, escalation paths defined, time-to-acknowledge measured | Tie to IR plan |
| 24x7 monitoring SLA documented and met (SI-4) | No SLA | SLA exists, not measured | SLA documented, measured monthly, MSSP or internal SOC evidenced | If MSSP, contract evidence required |
| Log integrity and access controlled (AU-9) | Logs writable by source admin | Read-only enforced, audit trail partial | Logs immutable, access audited, access reviews running | Common assessor probe |
Section F: Incident response and resilience (10 points; 5 items, raw maximum 10)
| Item | 0 | 1 | 2 | Notes |
|---|---|---|---|---|
| Documented IR plan tied to in-scope systems (IR-1, IR-8) | Plan generic or > 12 months stale | Plan current, not exercised | Plan current, exercised within 12 months, post-exercise corrective actions tracked | The exercise is the artifact |
| Tabletop exercise within last 12 months with findings (IR-3) | No tabletop | Tabletop run, findings not actioned | Tabletop run, findings ticketed, corrective actions closed | Targeting Measured means findings tracked to closure |
| BCP / DRP with documented RTO and RPO (CP-2) | No documented RTO/RPO | RTO/RPO drafted, not validated | RTO/RPO documented per critical system, validated against last test | Often the longest remediation line item |
| DR test executed within 12 months (CP-4) | No test | Tabletop only, no failover | Failover tested, evidence captured, gaps remediated | Healthcare SaaS reliably struggles here |
| Backup integrity and restoration tested (CP-9, CP-10) | Backups not tested | Restore tested ad-hoc | Restore tested on cadence, integrity verified, evidence in MyCSF | Includes immutable / offline copy |
Section G: Evidence and MyCSF documentation (15 points; 7 items, raw maximum 14)
| Item | 0 | 1 | 2 | Notes |
|---|---|---|---|---|
| Evidence designed automated where feasible | All manual screenshots | Mix, automation in flight | Automated evidence (queries, exports, scheduled jobs) wherever feasible, manual only where required | Year-2 cost concentrates here |
| Evidence tied to operative practice, not just policy | Policy uploaded as evidence | Procedure uploaded, no operative artifact | Operative artifact (ticket, log, export, screenshot) tied to control narrative | Implemented is shown by practice, not by policy |
| Assessor narrative drafted per domain | No narratives | Narratives drafted for some domains | Narratives drafted for all 19 domains, reviewed by readiness partner | The assessor reads these first |
| Scoring rationale documented per control | Scoring undocumented | Scoring documented for high-impact controls | Scoring rationale documented for every in-scope control, tied to evidence | What HITRUST QA reviews |
| Evidence freshness within authoritative source window | > 50% stale | 10–50% stale | < 10% stale, freshness tracked, refresh cadence | Common QA finding |
| MyCSF organized for assessor self-service | Assessor depends on screen-share | Partial structure | Folder taxonomy, naming convention, cross-links from narrative to evidence | Saves weeks in months 8 to 9 |
| Control-owner attestation captured per control family | No attestations | Attestations partial | Named control owner attested, dated, recorded in MyCSF | The Managed maturity question |
Section H: Internal effort and FTE coverage (5 points; 3 items, raw maximum 6)
| Item | 0 | 1 | 2 | Notes |
|---|---|---|---|---|
| Single named MyCSF owner, dedicated | No owner or owner is a committee | Owner named, under 75% allocated | One owner, ≥ 75% allocated for the engagement, other duties reassigned | The roadmap's non-negotiable |
| Dedicated remediation lead distinct from MyCSF owner | No remediation lead | Lead named, fragmented | Lead named, dedicated, gap register is their source of truth | Two people, two roles |
| Named control owners across 19 domains | Owners not assigned | Owners partial | Every domain has named owner, recorded in MyCSF, attestation captured | Domain coverage check |
Total and interpretation
Convert each section's raw points to its weight and sum the section scores, rounding to the nearest whole number. The total possible is 100 (10 + 15 + 15 + 15 + 15 + 10 + 15 + 5); the pass threshold is 80.
- 80 to 100: High probability of first-attempt validated certification. The assessor's review should surface clarification questions more than findings, and the HITRUST QA exchange is less likely to require resubmission. Continue execution as planned. Use the remaining months to close any 1s into 2s and to organize MyCSF for assessor self-service.
- 65 to 79: Needs a focused two- to three-month remediation push. First-attempt certification is achievable but not free. Identify the lowest-scoring section and concentrate remediation effort there. Common rescue patterns are tightening BC/DR (Section F), closing vendor reassessment cadence (Section C), and bringing evidence to operative-practice maturity (Section G).
- 50 to 64: Re-baseline. The eleven-month plan is at risk. Two responsible options: extend the calendar by two to four months and re-engage the assessor on a revised window, or step the assessment down to e1 / i1 for the current cycle and re-target r2 the following year. Either path is honest; pretending the program is on track is not.
- Under 50: Do not enter the validated assessment window. Burning the assessor engagement against this posture spends the assessor fee and ends with a withdrawn assessment, not a certification. Pause, re-baseline scope, and rebuild the gap register from the current state.
What the readiness partner does at each band
At 80 and above, the partner's role narrows to QA, reviewing assessor narratives, pressure-testing scoring rationale, and rehearsing the assessor walkthroughs. At 65 to 79, the partner re-prioritizes the gap register against the lowest-scoring sections and runs weekly remediation standups against the new sequencing. At 50 to 64, the partner runs the re-baseline conversation with the executive sponsor, including the conversation with the validated assessor about extending the engagement window, and the conversation with the customer driving the r2 requirement about a revised commitment date. Below 50, the partner runs the stand-down conversation, documents the lessons in a corrective action plan, and resets the scope conversation before any further calendar is committed. Each of those roles is part of the HITRUST and SOC 2 readiness work in our security and governance practice.
What this scorecard is not
This scorecard does not bind the validated assessor and it does not bind HITRUST. The assessor's scoring decisions and HITRUST's QA judgment are independent; a high score here forecasts but does not guarantee them. It does not encode any state-board, payer-specific, or contractual overlay, for example, a particular health system customer may impose evidence requirements above and beyond the r2 control set, and those overlays must be tracked separately. The notes that mention Measured and Managed apply where the assessment scores those levels; an org targeting them across all domains should treat 80 as the floor, not the bar. The scoring weights are frozen at the lastReviewed date in the frontmatter, 2026-11-14; check them against the current CSF version and HITRUST's current QA submission process before relying on them.